Case Study  |  Education

School Kitchen Renovation – Race Leys School

Client
Griffen Schools Trust – Race Leys School
Sector
Education
Completed
August 2022
01

Project Overview

JAF Property Group was commissioned by Race Leys School to deliver a comprehensive renovation of the school’s main kitchen facility. The project involved a full strip-out of the existing infrastructure followed by a complete rebuild to ensure compliance with updated fire safety, hygiene and operational regulations. Working closely with CaterKwik, our team prepared the kitchen shell and all essential services ahead of the installation of new commercial equipment, appliances and worktops.

02

Our Works

Strip-Out & Disposal

  • Removal and safe disposal of all existing flooring materials.
  • Complete removal of all wall cladding throughout the kitchen area.
  • On-site skip management for continuous waste removal, located adjacent to the rear kitchen door for easy access.

 

Flooring Replacement

  • Supply and installation of commercial-grade non-slip vinyl flooring with a hygienic Cap & Cove finish.

Wall Reconstruction & Compliance

To achieve compliance with current fire and hygiene regulations, all kitchen walls were reconstructed using:

  • New wall stud framing
  • 12mm plywood backing
  • Fire-rated 12mm plasterboard
  • Full-height Altro Whiterock hygienic wall panels

Construction of New ‘Service Spine’ Partition

A new central half-height partition (‘Service Spine’) was constructed to facilitate service distribution and improve kitchen workflow.

  • Built and clad with fire-rated plasterboard
  • Finished with Altro Whiterock
  • Integrated electrical points and sockets to meet the client’s specification
  • Electrical feeds routed through pillar conduit from the suspended ceiling into the Service Spine

Electrical Upgrades

To support modern commercial kitchen equipment, the electrical system was upgraded to 3-phase:

  • Installation of a new 3-phase main supply cable from the existing fuse box, routed across the hall at high level
  • Supply and installation of all new electrical cabling
  • Fitting of upgraded plug sockets and electrical outlets per CaterKwik’s design

Plumbing Works

Plumbing services were modified to suit the new layout:

  • Rerouting of all supply and drainage services
  • Installation of a new waste channel outlet
  • Upgrading and converting existing pipes and connections

Additional Finishing Works

  • Preparation and repainting of door frames for the toilet and storage rooms
  • Final cleaning, waste removal and site preparation for the incoming CaterKwik installation team
03

Gallery Of Works

04

Our Partnership

Completed on 31 August 2022, the Race Leys School kitchen refurbishment was delivered on schedule before the new academic year. JAF Property Group transformed the outdated kitchen into a fully compliant, modernised shell ready for the installation of new commercial appliances.

The result is a safer, more efficient and regulation-compliant food preparation environment that will serve the school’s needs for years to come. Our team worked seamlessly with external specialists and completed all works within the school’s summer closure period, minimising disruption.